Real estate projects to get only 1-year deadline extension

 88 Page views  

MUMBAI: The central government, which had jolted builders when it introduced a real estate regulatory law last year, maintained that a limited permissible one-year extension on completion deadline under the Act was mandatory, not discretionary. 

A Bombay high court bench of Justices Naresh Patil and R G Ketkar on Wednesday asked additional solicitor general Anil Singh, who appeared for the Centre, if a provision under the Real Estate (Regulation & Development) Act was mandatory or directory. Senior counsel Aspi Chinoy, who represents a leading builders' group that challenged the validity of the section which bars the RERA authority from giving any further extension beyond a year, was "unreasonable and unworkable'' as it failed to take cognizance of industry-specific force majeure events and accepts only war or acts of God.

Singh said the one-year deadline cannot be allowed to be extended as builders would take advantage of such leeway and the vexed issue of delay in completion of projects will continue, instead of being rectified, which the Act was meant to do. 

There was also a discussion on whether the 70% amounts raised by the builder for a project, which the Act requires him to deposit in a separate account while registering the project, should apply to on-going projects. The bench said if the builder had already used the amount for the 'past word', there would be no need to deposit it, but if not utilized, it could be deposited. 

Chinoy said the Act and Maharashtra rules made it clear that on-going projects were spared for work done earlier but the deposit would be prospective, from "amounts to be realised'' from allottees or buyers. 

Singh, however pointed to a Delhi rule on RERA which said that when an on-going project is being registered 70% of the amount realized must be deposited in a separate bank account. Several states have similar rules, he pointed out. 

The hearing will continue on Thursday, with the Centre seeking to justify why the provisions are not discriminatory nor unreasonable , but meant to bring in transparency in the real estate sector to save buyers from hardships.

Latest Post :

Last 05 Jun. 2026

Delhi–Siliguri Bullet Train Announced: Via Lucknow, Varanasi And Patna, Travel Time To Drop From 20 Hours To 6

Last 21 May. 2026

Delhi to Jewar Airport in 21 minutes: New RRTS corridor to link Noida Airport with Varanasi bullet train

Last 11 May. 2026

L-G directs DDA to chart out plan to develop Dwarka into an international investment hub

Last 10 May. 2026

New 10-Lane Delhi-Jewar Corridor Planned Ahead Of Noida Airport Launch

Last 08 May. 2026

Now homeowners can file online complaint against builders for illegal transfer charges in Uttar Pradesh; Step-by-step guide on how to do it