UPSBCL claims the Authority has not cleared payments related to price escalation, extra GST, and interest on delayed payments, pushing total dues to around ₹150 crore. Although the 5.5km, six-lane elevated road was completed and handed over in August 2025, the corporation says months of reminders have gone unanswered.

The dispute formally escalated last year. UPSBCL first invoked the arbitration clause on November 12, 2024, and followed up on May 7, 2025 with a panel of three proposed arbitrators.

A final reminder on June 5 expressed willingness for conciliation if payments were released.

With no response, UPSBCL moved the Allahabad High Court under Section 11 of the Arbitration and Conciliation Act, seeking appointment of a sole arbitrator.

The corporation has also refused to finish ancillary works—service roads and drainage lines under the flyover—unless dues are settled or an additional ₹25 crore is sanctioned. These surface works are crucial to prevent traffic bottlenecks and waterlogging, especially in Bhangel, Barola and adjoining sectors.

Authority officials, however, maintain that UPSBCL must complete the tasks listed in the original agreement. “They cannot walk away from their contractual responsibilities. Service roads and drains are part of the contract,” a senior official said.

UPSBCL was unavailable for a response on the matter.

On November 18, the elevated stretch was opened to the public following residents’ pressure, but the damaged and unfinished surface road below remains a major chokepoint, leaving thousands of commuters stuck amid the unresolved standoff.


Latest Post :

Last 05 Jun. 2026

Delhi–Siliguri Bullet Train Announced: Via Lucknow, Varanasi And Patna, Travel Time To Drop From 20 Hours To 6

Last 21 May. 2026

Delhi to Jewar Airport in 21 minutes: New RRTS corridor to link Noida Airport with Varanasi bullet train

Last 11 May. 2026

L-G directs DDA to chart out plan to develop Dwarka into an international investment hub

Last 10 May. 2026

New 10-Lane Delhi-Jewar Corridor Planned Ahead Of Noida Airport Launch

Last 08 May. 2026

Now homeowners can file online complaint against builders for illegal transfer charges in Uttar Pradesh; Step-by-step guide on how to do it