Published on Wed Jan 04 2023 | The Metro Rail Guy HG Infra Delhi Metro Vikaspuri Mangolpuri Janakpuri West RK Ashram Extension Haiderpur Delhi Metro Rail Corporation (DMRC) China Civil Engineering Construction Corporation (CCECC ) KEC International Keshopur Paschim Vihar Peeragarhi
H.G. Infra Engineering Ltd. in December-end was declared as the lowest bidder to construct 3.5 km Package DC-01A (Vikaspuri Ramp – Mangolpuri) of Delhi Metro Magenta Lines's 28.92 km Janakpuri West – RK Ashram extension.
This elevated section with 4 stations was originally a part of the Delhi Metro Phase 4 project's 12.375 km Package DC-01 connecting Vikaspuri Ramp and Haiderpur-Badli Mor Station via 10 stations.
Delhi Metro Rail Corporation (DMRC) had awarded its construction contract in November 2019 to China Civil Engineering Construction Corporation – KEC International (CCECC – KEC) JV with a deadline of 30 months.
Construction work was launched in December 2019 wherever a clear right-of-way was available, but portions of the Vikaspuri Ramp – Mangolpuri section were held up for years due to pending permission approvals to cut trees enroute.
After negotiations between CCECC – KEC and DMRC, this section was offloaded from DC-01’s scope. DMRC carved it into a separate package DC-01A and invited tenders for its construction in September with a 24 month deadline and Rs. 398.63 crore estimate. Technical bids were opened in November to reveal 3 bidders.
| Firm | Bid (Rs. Crore) |
| H.G. Infra Engineering Ltd. | 413.60 |
| Sam India Builtwell Pvt. Ltd. | 419.58 |
| KEC International Ltd. | 450.61 |
Brief Scope: Part Design and Construction of Elevated Viaduct and four Elevated Stations viz. Keshopur, Paschim Vihar, Peeragarhi & Mangolpuri (Excluding Architectural Finishing works of stations, Steel FOB & PEB works of stations) from P2 (excl.) to PP88 (excl.) [Chainage 3118.108 mt. to 6080.447 mt.] and from P103 (excl.) to Mangolpuri Station (incl.) [Chainage
6462.547 mt. to 7012.051 mt.] of Janakpuri West to R.K. Ashram Corridor (Extn. of Line-8) of Phase- IV of Delhi MRTS
HG Infra’s bid was just 3.76% higher than DMRC’s estimate, so a contract should be awarded in the coming weeks without a long financial bid evaluation period. I expect site preparation to begin in March with actual construction starting in Q2.
A list of all Delhi Metro Phase 4 packages, their contractors and status can be viewed here.
Delhi–Siliguri Bullet Train Announced: Via Lucknow, Varanasi And Patna, Travel Time To Drop From 20 Hours To 6
Delhi to Jewar Airport in 21 minutes: New RRTS corridor to link Noida Airport with Varanasi bullet train
L-G directs DDA to chart out plan to develop Dwarka into an international investment hub
New 10-Lane Delhi-Jewar Corridor Planned Ahead Of Noida Airport Launch
Now homeowners can file online complaint against builders for illegal transfer charges in Uttar Pradesh; Step-by-step guide on how to do it