Published on Tue May 13 2025 | The Indian Express Delhi Meerut The National Capital Region Transport Corporation (NCRTC) Regional Rapid Transit System (RRTS) Ghaziabad Uttar Pradesh Duhai Sahibabad New Ashok Nagar
For the first time in India, precast track slabs have also been used at track turnouts — junctions where trains can switch from one track to another
The National Capital Region Transport Corporation (NCRTC) has completed the installation of all 169 track km (TKM) of precast slab track on the Delhi-Ghaziabad-Meerut corridor of India’s first semi-high-speed Regional Rapid Transit System (RRTS).
Precast slabs are those that are manufactured elsewhere and then brought to the site, instead of being manufactured on the site.
According to NCRTC, the work involved the production and laying of nearly 47,000 high-precision precast concrete slabs that will form the base of the railway tracks. These have been installed across both elevated and underground sections of the corridor.
For the first time in India, precast track slabs have also been used at track turnouts — junctions where trains can switch from one track to another. A total of 135 such turnouts, involving eight different configurations and 15 slabs each, have been installed.
In total, the project used slabs of 140 different types, making logistics and inventory management a major challenge during execution.
The track system is designed to support trial speeds of up to 180 kmph and an operational speed of 160 kmph.
At present, trains are undergoing trial runs at higher speeds on certain sections. Officials said that the track’s performance is critical to safety and reliability in a high-speed rail system, especially since such systems lack redundancy — there is usually no backup track available in case of failure.
The slab track system was selected through a detailed process involving international technology transfer. From design and equipment selection to training and troubleshooting, the system provider was involved throughout the implementation phase.
Currently, 55 km of the corridor — from New Ashok Nagar in Delhi to Meerut South in Uttar Pradesh — has been commissioned and is operational.
Trial runs are underway on other stretches, with the entire 82-km corridor expected to become fully operational by June 2025.
A timeline of the project
-October 2023: 17-km Priority Section between Sahibabad and Duhai Depot inaugurated
-March 2024: 17 km stretch between Duhai and Modinagar North inaugurated
-August 2024: Meerut South RRTS Station operationalised
January 2025: 13 km stretch between Sahibabad and New Ashok Nagar inaugurated by PM Narendra Modi
-June 2025: Complete Delhi-Meerut corridor expected to be operational
Delhi–Siliguri Bullet Train Announced: Via Lucknow, Varanasi And Patna, Travel Time To Drop From 20 Hours To 6
Delhi to Jewar Airport in 21 minutes: New RRTS corridor to link Noida Airport with Varanasi bullet train
L-G directs DDA to chart out plan to develop Dwarka into an international investment hub
New 10-Lane Delhi-Jewar Corridor Planned Ahead Of Noida Airport Launch
Now homeowners can file online complaint against builders for illegal transfer charges in Uttar Pradesh; Step-by-step guide on how to do it